  • Who will pay for MoPac cost overruns? Agency, contractor deal in sight

    10/09/2017 2:13:03 PM PDT · by Tolerance Sucks Rocks · 20 replies
    The Austin American-Statesman ^ | September 24, 2017 | Ben Wear
    They’ve butted heads and talked of lawsuits as the MoPac Boulevard toll lane construction project has dragged on two years beyond its target completion date. Now the Central Texas Regional Mobility Authority and its toll project contractor appear to be near a financial settlement. The mobility authority board, in a specially called meeting scheduled for Tuesday morning, will consider an agreement with CH2M, the Denver-based engineering and construction firm that in April 2013 agreed to design and build the 11-mile project. The contractor agreed then to a fixed price of $137 million. But in a March 2017 memo, written when...