Expansion work is to begin at the Aluto-Langano Geo-thermal Power Plant, in February, with the delivery of equipment to the site. The project, estimated to cost 35 million dollars, has already had 17 containers of materials delivered, with 10 more currently at the dry port, according to Miskir Negash, public relations officer of the Ethiopian Electric Power Corporation (EEPCo). The Corporation will also import 400tn of international standard cement over the coming few weeks, Miskir said. The expansion includes the digging of four wells, up to 2,500m deep, boosting Aluto-Langano's geo-thermal capacity to 70Mw; the total potential for the country...