EDITORIAL: Down the road to a priority road project
The Columbia Times and Democrat Adware Farm ^ | May 19, 2021 | Times and Democrat Editorial Board

Posted on 05/25/2021 3:00:12 PM PDT by Tolerance Sucks Rocks

The entire $1.7 billion Carolina Crossroads project is broken down into five phases. The plan is to provide a safer, more modern interchange design for the state’s top interstate “pinch point,” commonly known as “Malfunction Junction” in the Midlands of South Carolina. More than 134,000 vehicles including commuters, freight carriers and other travelers pass through this area on a daily basis.

Phase I of the Carolina Crossroads project will center on the reconfiguration of the Colonial Life Boulevard interchange on I-126. Some improvements will be made to improve traffic flow along I-26 heading in the direction U.S. 378. This project will be undertaken by the joint venture team using the innovative “designed-build” method. This strategy will allow the final design work and construction to be completed by a proven team of industry experts on an expedited schedule.

The contract signing marks the beginning of work to finalize the design and other preconstruction activities for the project. The public should expect seeing major construction activity beginning in spring 2022 with all the work associated with the Phase 1 project being completed by the end of 2024.

Secretary of Transportation Christy A. Hall says that SCDOT looks forward to partnering with Archer-United to make the start of this long-awaited project a reality for the South Carolina.

“The upgrade and modernization of the intersection of I-20, I-26 and I-126 is critical to our economic vitality and will enhance the daily commute for thousands of South Carolinians. The team of Archer-United has an excellent track record of delivering good, quality projects on time and on budget and I look forward to the improvements beginning on this critical project for the State of South Carolina.“

(Excerpt) Read more at thetandd.com ...


TOPICS: Business/Economy; Chit/Chat; History; Local News; Miscellaneous; Outdoors; Society; Travel
KEYWORDS: 10yearplan; 2029; archerunited; carolinacrossroads; columbia; congestion; construction; designbuild; i126; i20; i26; infrastructure; interchanges; interstates; malfunctionjunction; midlands; safety; scdot; southcarolina; traffic; transportation; us378; widening

1 posted on 05/25/2021 3:00:12 PM PDT by Tolerance Sucks Rocks
[ Post Reply | Private Reply | View Replies]

To: Tolerance Sucks Rocks

1.7 billion and 2 years? I don’t know about South Carolina but if it were California it would be 10 years and 17 billion by the time it was done.


2 posted on 05/25/2021 3:03:13 PM PDT by Seruzawa (The political Left is the Garden of Eden of Incompetence - Marx the Smarter (Groucho))
[ Post Reply | Private Reply | To 1 | View Replies]

To: BobL; sphinx; GreenLanternCorps; oldvirginian; Haiku Guy; napscoordinator; ConservativeInPA; ...

PING!


3 posted on 05/25/2021 3:03:23 PM PDT by Tolerance Sucks Rocks (Florida: America's new free zone.)
[ Post Reply | Private Reply | To 1 | View Replies]

To: Seruzawa

To be sure, that’s the first of 5 phases. The entire project is expected to be completed in 2029.


4 posted on 05/25/2021 3:07:02 PM PDT by Tolerance Sucks Rocks (Florida: America's new free zone.)
[ Post Reply | Private Reply | To 2 | View Replies]

To: Tolerance Sucks Rocks

These sort of contract proposals often cost a JV like this 100k to 200k to put together all the proposals, preliminary pricing and design needed to secure this contract or submit for the final running.

It often takes the involvement of 30 to 50 staff members from each JV partner for two to four months.


5 posted on 05/25/2021 3:23:33 PM PDT by KC Burke (If all the world is a stage, I would like to request my lighting be adjusted.)
[ Post Reply | Private Reply | To 4 | View Replies]

To: Seruzawa

Wait.

When?

Haven’t they heard? The planet will be over by then. Climate Scientist AOC said so.


6 posted on 05/25/2021 3:46:00 PM PDT by T. Rustin Noone (the angels wanna wear my red shoes......)
[ Post Reply | Private Reply | To 2 | View Replies]

To: Tolerance Sucks Rocks
The entire project is expected to be completed in 2029 3029.

Fixed it.

7 posted on 05/25/2021 3:59:30 PM PDT by Seruzawa (The political Left is the Garden of Eden of Incompetence - Marx the Smarter (Groucho))
[ Post Reply | Private Reply | To 4 | View Replies]

To: Seruzawa

Cue Zagar and Evans. Or Philip J. Fry.


8 posted on 05/26/2021 1:17:02 PM PDT by Tolerance Sucks Rocks (Florida: America's new free zone.)
[ Post Reply | Private Reply | To 7 | View Replies]

Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.

Free Republic
Browse · Search
General/Chat
Topics · Post Article

FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson