Posted on 11/07/2005 8:54:03 PM PST by jeffers
New Orleans Levee Failure Analysis - Part V
Contents
Introduction and Basic Levee Construction, Section and Elevation Details
Section 1. Pre-Landfall Flooding in Kenner and Western Metairie of East Jefferson Parish
Section 2. Analysis of the 17th Street and London Canal Breaches and Post Katrina Flood Sequence in Downtown New Orleans
Section 3. Surge Sequence for the Industrial Canal Basin, Analysis of the Five Major Breaches and east Orleans Parish Flooding
Section 4. Flood Sequence for St. Bernard Parish and the Lower Ninth Ward, MRGO Reach Failure Analysis
Section 5. Contributory Causality, Political and Funding Issues Leading to Levee Failures
Introduction:
This is part five of a five part series analyzing and assessing the New Orleans flood resulting from landfall of Hurricane Katrina. Parts 1 through 4 can be found at the links below.
Part 1 is a timeline sequence of who reported what flood events and when it was reported. It can be found here:
Part I: Hurricane Katrina Flood Report Sequence
Part 2 is a discussion of the levee system's subsidence prior to Hurricane Katrina. It can be found here:
Part II: Pre-Katrina Levee Assessment
Part 3 is a discussion of the overall storm surge sequence and levee failure mechanisms relating to the 17th Street Canal and London Canal seawall breaches. It can be found here:
Part III: Downtown New Orleans Levee Failures
Part 4 is a discussion of breaching and topping in St. Bernards and east Orleans Parish. it can be found here:
Part IV: New Orleans Levee Failure Assessment
Some elements of this discussion will occur out of the sequence in which they occurred, to facilitate understanding of the processes involved, and to minimize the bandwidth required to download similar images more than once. The correct sequence would be
1. Pre-Katrina Flooding in Kenner
2. MRGO Topping and Breaching
3. Industrial Canal Breaching
4. St. Bernard Parish Flooding
5. Flooding from the 17th and London Canal Breaches
In this discussion, issues involving the 17th Street Canal and London Canal Breaches are instead discussed immediately following the PreKatrina Kenner Flooding, since both sets of events affected overlapping areas and use similar graphics.
Analysis and conclusions for levee failures and flooding in Plaquemines Parish is largely omitted in this effort. The Plaquemines levees were designed for a maximum Categtory 3 storm, were instead subject to Category 4 winds and Category 5 storm surge, and simply failed under loads that exceeded anything they were designed to withstand.
Basic Levee Construction
Two main types of levee protection systems were in general use prior to Katrina's landfall, one being older earthen levees, modernized and raised with the addition of concrete capwalls, commonly referred to as an I-wall, and typically in service around downtown New Orleans and the Industrial Canal area, and the other being earthen levees in use around the remaining three sides of east Orleans and St. Bernard Parish.
The following images detail typical examples of the concrete capwall (I-wall) type levees in use around downtown New Orleans and the Industrial Canal, and were obtained from Army Corps of Engineers Field Engineering Manuals, specifically "Design and Construction of Levees", "Retaining and Flood Walls", and "Design of Sheet Pile Walls", all available at:
CoE Engineering Manuals http://www.usace.army.mil/inet/usace-docs/eng-manuals/em.htm
In the case of the 17th Street and London Canal levees, the sheet piles were driven to depths of 17.5 and 16 feet respectively.
The image below is a typical cross section of an earthen levee, similar to the type in service along the northern, eastern, and southern reaches of east Orleans and St. Bernards Parishes.
Generally, the failed sections of earthen levee around St. Bernard and east Orleans Parishes do not appear to have included sheetpiling or other core construction. In a very few instances, evidence of a sheetpile core is now exposed and in general, these occurrences tend to be present where older pre-existing canals and natural waterways cut across the levee's intended location, probably due to recognition that otherwise seepage and percolation would be more of a problem at these locations.
That's good to know, I'll keep it in the "possible" drawer for future reference.
I'm not sure I got this across in the main text, and it leads to something I left out, so...
Here's a pile of dirt, 700 feet long, 30 to 50 feet thick, the old levee embankment. On top of it is a concrete wall, eyeball says 10 feet tall, and the specs say 2 feet thick at the base, 1 foot thick at the top, each lineal foot of capwall weighing about, oh, twelve lineal feet of concrete sidewalk, a LOT of weight.
We know it failed, which means that the water pressure at some point exceeded the I-Wall's resistance to lateral displacement, which further means that at some earlier point the opposing forces exactly balanced.
Ever drive around a curve on ice and feel your car go "up on her toes" on the edge of a skid?
Seven hundred feet of heavy earthen embankment and concrete was balanced like that, essentially resting on ball bearings, before it failed. Because we know the weak layer was extensive, probably orders of magnitude more levee was in that perfectly balanced condition or very close to it at some point during the storm's passage.
Not to scare you, because any breach wider than the width of the canal where it connects to the Lake will not speed the flooding of the city up by much, whether it's a foot wider than the canal outlet, or a mile wider than the canal outlet. A wider breach will drain the canal faster, but then the limiting factor becomes the narrowest point in the canal between Lake and breach.
Anyway, the point here is, while large sections of levee were in such a precarious position, just about anything coud have caused a breach. A disruption from a felled tree's root ball thirty years ago in the embankment, one nutria tunnel, one shingle blown off a neighboring house and hitting the levee at 85 mph might have done it. A non-compliant swimming pool excavation could be akin to a speeding locomotive broadsiding your car on the icy curve by comparison. Yes, that would certainly do the trick.
While the 17th Street Canal breach is under discussion, the subject of the old court case involving the contractor who claimed weak soil needs to be addressed. MSNBC linked to an online version of the judge's decision in that case, but plastered their logo all over it so you couldn't read it.
That wasn't an accident. They didn't want you to read it because it blew their whole story line out of the water. The best laid plans, however...
If you really want to read it, you need to download the PDF file, open it, and open an image browser. Flip to page 2, hold your finger over the "Prtscrn" (Print screen) key on your keyboard, flip back to page 1, and hit Printscreen before the NBC logo loads, it is the last layer to be rendered. Then just go to your image browser, open a New image, paste the clipboard contents to the image, zoom to 100% and read what they never wanted you to read.
The judge's decision clearly demonstrates that this case involved a less than competent contractor trying to scam his way out of a jam.
Basically, he failed to brace his concrete forms properly, and the wet concrete pushed them around, and the wall sections set-up ("dried" to most people) crooked.
When the Corps of Engineers called him on it, he said the CoE had misrepresented conditions at the worksite. The CoE said to state their case in writing, make an official report describing what the contractor was claiming the CoE said about the worksite that turned out not to be true.
The contractor took a very long time responding to that request, basically giving the CoE the report shortly before the case went to court.
The contractor claimed that the CoE misrepresented the strength of the soil.
The CoE replied, "How would you know? You never bothered to request our soil testing data before submitting a bid. All the OTHER companies did. In fact, you never requested the data at all until your concrete went crooked due to sloppy form bracing and we called you on it."
At that point the contractor claimed that weak soil allowed the form brace anchors to wobble.
The CoE's response was that it was poor construction practice to try and brace forms to support heavy wet concrete on anchors driven only six feet in the ground, and that further, the CoE had no say in bracing techniques, that responsibility for bracing was explicitly assigned to the contractor in the standard contract that he had signed, and that finally, another contractor nearby had performed flawless work under the same conditions.
The judge was not amused, the contractor did NOT win the case, the contractor later went bankrupt, and NBC plastered their logo all over the "supporting documents" for their story because they didn't want you to read those documents, because then you would know that their whole "CoE Warned About Weak Soil Long Before Katrina" storyline was a pile of nutria squat.
An unproven....no....actually a disproven claim of "weak soil" at six feet below grade, has exactly zero bearing on a demonstrated weak layer at 15 to 20 feet below grade.
All it accomplishes is to demonstrate how far NBC is willing to go to pin the blame anywhere besides where it actually belongs.
Bump
The media might make use of some of this information, there is a demonstrated market for levee failure information considering how many other stories they've printed. Then again, they might not be interested, this early, anyway.
No matter. I want this to gel for a while, and I've got some catching up to do around the homestead, which will allow the engineer and construction types here to poke holes in the analysis if possible so problems can be addressed and cleaned up if they surface.
Then I plan to point Al Naomi and a few other CoE types here, so they will know which way the wind is set to blow and make sure they don't step into a pile of weak soil.
If they don't poke any substantiated, logical holes in it, the next step is the Senate Investigative Committee.
By the time their report is completed or before, I expect the media might have to mention it, on page 29D if nothing else.
No matter.
The Senate Investigation Report is what will decide...oh....about 250 billion dollars worth of wrongful death and damage resulting from malicious negligence lawsuits.
Those suits in turn have significant impact on Louisiana's financial viability over the long term, and most importantly, the re-election hopes of certain politicians.
Reporters will be reporters.
And lawyers will be lawyers.
Obtaining justice, like many other projects, is often a matter of selecting the proper tools and techniques. In this case, certain people simply cannot allow the truth to surface and survive. They seem to think the matter will be settled in the court of public opinion, and that since they hold good cards there, they will get off scott free.
They may have miscalculated.
No.
Thank you.
For those of you not familiar with Ellesu's work, she has put in countless hours researching and posting information from Louisiana and other sources that help the rest of us understand how things work down there.
Without that data, much of the content of these levee assessments would not have been possible.
If anyone deserves a National Medal it is you.
This information deserves attention. I was at my massage therapist last night and she was telling me what one of her demoncrat clients was telling her as gospel about NOLA.... couldn't be farther from reality... for instance... did you know they couldn't use the buses because the buses were defective because the state is/was so poor that they couldn't afford to get them fixed? or... the old levees broke because they didn't have the money to fix them...
So, yes, this information needs to be out and get some play.
I've been in awe of your diligence on this since the very beginning of this whole debacle. Thank you!
Ellesu my hat is off to you as well... thank you and Jeffers.
You are too kind. Thanks.
Thank You.
This is supposes to zoom in the house with the pool by the break--I can't make it work but you may have to piece this link together to find it. Let me know if you get it to work.
http://maps.google.com/maps?
q=17th+street+canal+New+Orleans,+LA+70124&ll=30.018041,-
90.120367&spn=0.003698,0.006951&t=k&hl=en
Ping to the FR Civil Engineerrs ping list.
Nice work Jeffers & Ellesu!
BTW, I kno walmost all of my CE pings have been on the NOLA levee failures. If you have something you thing the CE list may like, let me know, please.
I find myself in complete agreement on all points.
A gallon of water weighs 8.2 lbs. Considering there were/are millions of gallons pushing against those levees all the time, any weak spot quickly becomes magnified.
People get M.S. and Ph.D. degrees for detailed, meticulous, correlated stuff like this.
Thanks -
bkmk sealevel of 17th street break?
This is not a photograph of the area immediately west of the London Avenue Canal. This is Lakeshore Drive at Lake Vista, which is west of Bayou St. John.
While most people familiar with the area will agree with you, the statement is technically correct as written.
In the image, east is down, and from the lower edge of the photograph to the closest point of the London Canal is roughly 4800 feet.
The image used comes from NOAA, available here:
http://ngs.woc.noaa.gov/katrina/090E30A_KATRINA.HTM
The sequence of aerial images was captured such that each image overlapped the previous one by approximately 50%. In other words, moving from one photograph to an entirely new area immediately adjacent to the original view requires jumping over the next image in sequence.
In downloading these images for analysis, I used image 24425546 as baseline for the entrance for the London Canal. This is ambiguous as several images cover that area, but for clarity I designated that one as a reference point.
The next image west of there, 24425551 includes most of the area shown in the above image, but it is not the one I used. I jumped over the redundant area and used the second image west of 24425546 for this report, number 24425556.
To allow the display of greater detail, only part of image 24425556 was used. These are large, high resolution aerial images, measuring 4096 by 4096 pixels, while the referenced image in this report is no more than 1200 x 800 pixels. In looking at the small section of the image as displayed here, it would be difficult to believe that the next image fully displaced to the east would include the London Canal, but it does.
Regardless of technical accuracy, your point has merit. As displayed, the description of the image could raise confusion, and should have been worded better.
Thanks for pointing this out.
That part of Lake Vista wasn't flooded. The lakefront levee didn't fail and the damage was on the exposed lake side of the levee. I don't see what this has to say about the breaks along either the 17th St. or London Ave. canals.
The highest levee elevation in this photo is situated where all the arrows point, not at the lower seawall that lies between the road (Lakeshore Dr) and the lake. The seawall is outside the floodgates.
Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.