West Alpine on hold {Fed delays Alaska developement}
Petroleum News ^ | Week of January 17, 2010 | Kristen Nelson

Posted on 01/16/2010 6:45:15 AM PST by thackney

Without corps permit, ConocoPhillips can’t start work in 2010-11 winter season

- - -

Work on ConocoPhillips Alaska’s Alpine West or CD-5 satellite — the first satellite planned for development in the National Petroleum Reserve-Alaska — has been delayed by at least a year. The company had planned to begin construction in the winter of 2010-11, with two winter construction seasons required.

While the company received permits it needs from the North Slope Borough and the State of Alaska, it has not received its 404 permit from the U.S. Army Corps of Engineers, Helene Harding, vice president of North Slope operations and development, told Petroleum News Jan. 14.

She said they’ve been getting a lot of questions on when the project will go ahead, and felt they needed to make the delay public. The corps has known since mid-December that lack of the permit would delay the project, she said.

Harding said the corps has said it is trying to do a diligent review.

“It seems for us it’s a little difficult to understand, given that they’ve had this since 2005 — basically the same permit that they’ve been able to work on since 2005. And there is an approved EIS with this development scenario so it’s quite disconcerting,” she said.

A spokeswoman for the Corps of Engineers told Petroleum News that the corps had no comment.

Alpine West, also called CD-5, is included in a 2004 Environmental Impact Statement which includes now-developed drill sites at CD-3 and CD-4 (Fiord and Nanuq), and other NPR-A drill sites at CD-6 and CD-7 (now called Greater Mooses Tooth 1 and 2), Harding said.

The preferred alternative for CD-5 in the EIS was a development with a bridge across the Nigliq Channel and a road connecting CD-5 with the main facilities at Alpine, she said.

Alpine is not connected to the North Slope road system but is accessed by ice road in the winter and by air.

The bridge issue

ConocoPhillips submitted a 404 permit to the corps in 2005 and “spent the next few years working on that,” Harding said.

But there were issues on the bridge location with Nuiqsut and Kuukpik, the village corporation for Nuiqsut, and while ConocoPhillips worked those issues in parallel with work on the corps permit, the project was put on hold and the permit withdrawn in 2008.

Harding arrived in Alaska in January 2008 and began working with Kuukpik and the Village of Nuiqsut on the bridge location. Local concerns were with fishing in the area originally proposed for the bridge and also with erosion, she said.

Agreement was reached to move the bridge to the south and the corps permit was basically re-submitted in December 2008.

With the exception of the bridge and pad locations, “it was pretty much the exact same permit,” Harding said.

The pad was moved because over the years ConocoPhillips had done “some more extended reach drilling into some of the area that we called Alpine West,” which led to the pad relocation.

The corps holdup

ConocoPhillips has “had extremely strong support” from Nuiqsut — the village corporation, the city and the Native village. “All three had done resolutions in support of this,” she said. The project also received support from the Alaska Department of Natural Resources, the North Slope Borough and the Arctic Slope Regional Corp., Harding said.

By September, however, ConocoPhillips realized “that things were not going as quickly as we’d hoped, so we really put on a pretty big push with the corps.”

Harding said ConocoPhillips told the corps it had to have the permit by the end of the year.

In fact the original deadline was early November because of long-lead items, but because of changes in the steel market and lowered demand, “we were able to push that out another two months.”

But without the corps permit — and a permit from the U.S. Coast Guard which can only be issued following the corps permit — the company lost its construction window for next year.

“We won’t be able to get prepared for that construction season without the approval to be able to go forward,” Harding said.

And it’s not just CD-5 because there are three other projects stacked up behind it: Fiord West, Greater Mooses Tooth 1 and Greater Mooses Tooth 2.

CD-5 has been pegged at about half a billion dollars, Harding said, and the others at a similar cost, so some $2 billion in work is on hold.

At least a year

The delay will be at least a year, Harding said, because ConocoPhillips doesn’t have a permit and if a permit is issued, the company doesn’t know what stipulations it will contain. “There’s always the chance that we don’t get what we’ve asked for in the permit,” she said. The EPA opposes the project, she said, and both EPA and Fish and Wildlife are opposed to taking oil across the Nigliq Channel on a bridge, and are asking for horizontal directional drilling under the channel.

Harding said that is what was done at the Colville River for Alpine, “except that’s sales oil and this would be three-phase fluid,” because CD-5 oil will be processed at Alpine.

It’s not the same as the Oooguruk field, where three-phase oil comes to shore in a pipeline, she said. The Oooguruk line is in a trench, “a very flat profile.” HDD under the Nigliq Channel would involve a pipeline with “very deep bends” to go under the channel, “so you have a lot more corrosion-erosion issues.”

And without a bridge there would have to be another airport across the Nigliq Channel. Harding said one thing ConocoPhillips has heard continuously from Nuiqsut “is they don’t like planes flying in this area.” Another runway increases the air traffic.

ConocoPhillips also has an agreement with Nuiqsut to fund up to $8 million for a road from the Alpine road system to Nuiqsut. The road would allow year-round access from Nuiqsut to Alpine, opening up employment opportunities, and would also give road access for Nuiqsut residents to some key hunting areas to the west.

A roadless development would also require larger pads, Harding said, because you wouldn’t have year-round access to Alpine, and would require, among other things, emergency response capability, “something we are definitely not comfortable with,” Harding said.

It could be done, she said, but it’s “a different level of capability due to the weather conditions out there. It’s much easier if you have a road to access it.”


TOPICS: News/Current Events; US: Alaska
KEYWORDS: energy; northslope; npra; oil

This another one of those leases democrats claim oil companies have leased but not developed. The multitude of permits for this facility have been held up for many years. I was on the initial design team of CD-5 back in 2005 for initial planning.

BLM>Alaska>Programs>Energy>Oil and Gas>National Petroleum Reserve - Alaska
http://www.blm.gov/ak/st/en/prog/energy/oil_gas/npra.html

a multitude of permit information can be found at:

CD5 Permit Applications - 2008:
http://www.conocophillipsalaska.com/permits/CD5%20Permit%20apps%202008/index.asp

1 posted on 01/16/2010 6:45:18 AM PST by thackney
[ Post Reply | Private Reply | View Replies]

To: proud_yank

CD5 ping

Delayed again...


2 posted on 01/16/2010 6:47:43 AM PST by thackney (life is fragile, handle with prayer)
[ Post Reply | Private Reply | To 1 | View Replies]

Some (not all) of the North Slope Oil/gas fields that have been drilled.


3 posted on 01/16/2010 6:58:08 AM PST by thackney (life is fragile, handle with prayer)
[ Post Reply | Private Reply | To 2 | View Replies]

To: thackney

Frustrating!


4 posted on 01/16/2010 7:07:09 AM PST by Dr. Bogus Pachysandra ( Ya can't pick up a turd by the clean end!)
[ Post Reply | Private Reply | To 3 | View Replies]

To: thackney

We continue to let the Federal government expand its powers way beyond those limited in the Constitution.

Other than armed insurrection what choices remain? It would appear that the election process has broken down with only a 2 party choice and the country be damned.

We have destroyed this country with the sports team mentality of the average voter. As long as my team wins I am happy!

Well that has not worked very well has it.

Anyone notice the number of cases before Federal Courts that have been rejected because a US Citizen does not have standing?

It would seem unless you have an arm cut off and are bleeding all over the courtroom floor, a US Citizen does not have standing any more.


5 posted on 01/16/2010 7:33:29 AM PST by Wurlitzer (Welcome to the new USSA (United Socialist States of Amerika))
[ Post Reply | Private Reply | To 1 | View Replies]

To: thackney
This another one of those leases democrats claim oil companies have leased but not developed.

Funny thing is I've actually heard some on the other side of the aisle make that statement too ;-)

I hope this goes through, always nice seeing work go forward.

I'm up now, man is it cold. I think the coldest over the last few days was -38 and windchill of about -75.
6 posted on 01/16/2010 1:37:22 PM PST by proud_yank (Socialism - An Answer In Search Of A Question For Over 100 Years)
[ Post Reply | Private Reply | To 2 | View Replies]

To: proud_yank

I once landed at Deadhorse and exited without much concern.

Wind was blowing heavily. I put my non-gloved hand on the metal handrail of the stairs, jerking it back in pain.

I bundled my coat around me because I hadn’t bothered to zip it up for the short walk to the terminal.

I ran inside thinking “DAMN ITS COLD”.

I looked at the weather screen. Windchill -72°F.

No gloves, open coat.

Be careful. The weather up there can be unforgiving and stupid (like mine) can be rather punishing.


7 posted on 01/16/2010 1:53:48 PM PST by thackney (life is fragile, handle with prayer)
[ Post Reply | Private Reply | To 6 | View Replies]

To: thackney

Ouch!! How was your hand? Have to be really careful to put gloves back on if you’re working outside and taking notes. Inside cooling fans can be the worst, since they’re usually pretty warm inside.

The stair rail getting off the plane is covered in pipe insulation and duct tape now, for good reason.

It doesn’t take any time at all to get cold especially with only a slight wind, and its amazing how quickly a truck will get cold too.

I went outside to see if its true about water crackling in the air. Didn’t get it to happen, but the remaining water inside the cup froze to the sides in only a few seconds. The droplets on the edge were so cold they’d stick to my lip.


8 posted on 01/16/2010 8:39:37 PM PST by proud_yank (Socialism - An Answer In Search Of A Question For Over 100 Years)
[ Post Reply | Private Reply | To 7 | View Replies]

To: proud_yank

My hand was fine, stuck it deep in my pockets and ran for the terminal doors.

I came close to damaging my hand taking pictures of some cable tray on a piperack.

When I finally noticed my fingers tingling, I put my glove back on. My fingers tingled for a couple weeks. Rather scary.


9 posted on 01/17/2010 5:54:20 PM PST by thackney (life is fragile, handle with prayer)
[ Post Reply | Private Reply | To 8 | View Replies]

Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.

Free Republic
Browse · Search
News/Activism
Topics · Post Article

FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson