We need some recent pictures of the 'fence'.. Layout was to be completed by the end of June, and the major building to begin by July 15th, which is Saturday.
That is what the recent update states here:
http://www.minutemanhq.com/bf/
...along with needing that $55 million from donors.
May 27 to June 30 Finished the first 2.5 mi. section of fence, applied for permission on next 7.5 mi., repaired vandalized fence, ordered steel, finalized fence design/civil engineering specifications, retained 2 local Arizona contractors who hire legally, started vetting volunteers for work crews, completed volunteer delivery of donated construction truck, continue next 7.5 mi., acquire vehicle barrier steel, install vehicle barrier, test/install fence camera technology, plan and implement 24x7 fence security.
So, 10 miles of fencing, including the vehicle barrier & cameras were to be done by June 30. Do we have any indication that it is actually complete?