Rapidus ramps as construction begins on 2nm wafer fab
The Register ^

Posted on 09/02/2023 4:20:51 AM PDT by FarCenter

Japan's Rapidus broke ground on its IIM-1 plant in Hokkaido on Friday, kicking off a flurry of hiring as the foundry upstart races to bring its 2nm wafer fab online by 2025.

During the ceremony, the company revealed they have already hired more than 200 people to bring the facility online on schedule, according to a Bloomberg report.

The government-backed foundry got its start a little over a year ago in a bid to compete with TSMC, Samsung Electronics, and Intel. It aims to roll out with mass-produced chips based on 2nm process technology by 2027, with pilot production slated for early 2025.

"We will complete the plant at an unprecedented speed, as the company name Rapidus implies," CEO Atsuyoshi Koike said in a statement.

Competing with TSMC and Samsung won't be easy. Both have fabs that are already producing chips based on their respective 3nm process nodes and are expected to bring 2nm process tech to market beginning in 2025.

Rapidus has reportedly received 370 billion yen ($2.5 billion) in government subsidies, and has solicited the help of IBM to produce chips on its 2nm gate-all-around transistor tech, which it demoed in early 2021.

...

Even if Rapidus manages to avoid these same hiring pitfalls, the company could run into trouble with the process tech it has licensed from IBM. In April, GlobalFoundries sued IBM, accusing the company of licensing its intellectual property to Intel and Rapidus when it had no right to do so. The lawsuit, which is still in the pre-trial phase, seeks an injunction that may derail the foundry operators' roadmaps.

(Excerpt) Read more at theregister.com ...


TOPICS: News/Current Events
KEYWORDS:

1 posted on 09/02/2023 4:20:51 AM PDT by FarCenter
[ Post Reply | Private Reply | View Replies]

To: FarCenter

From the article: “ A shortage of skilled workers necessary to install and operate chipmaking equipment has already forced delays at TSMC’s Arizona fab sites.

In July, TSMC CEO, Mark Liu, said the company couldn’t find enough workers to install sensitive chip making equipment and that production of 4nm chips at the plant would be delayed until sometime in 2024 because of this. As a stopgap, the company plans to send technicians from Taiwan to assist and train local hires to prevent further delays to the project.

Intel has also stepped up training and recruitment efforts as it expands its foundry footprint in anticipation of competing with TSMC, Samsung, and others on leading-edge chip production. In July the x86 giant told The Register that the semiconductor industry could face a shortage of 70,000 to 90,000 workers over the next few years, and that it’s working with universities, community colleges, and the National Science Foundation to establish a talent pipeline to attract fresh staff.”

Do we retrain English, Psychology, and Gender Studies grads, or do we train illiterate illegals to fill this gap?


2 posted on 09/02/2023 5:30:17 AM PDT by VanShuyten ("...that all the donkeys were dead. I know nothing as to the fate of the less valuable animals)
[ Post Reply | Private Reply | To 1 | View Replies]

To: VanShuyten

#BraveWomen


3 posted on 09/02/2023 6:22:03 AM PDT by EEGator
[ Post Reply | Private Reply | To 2 | View Replies]

Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.

Free Republic
Browse · Search
News/Activism
Topics · Post Article

FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson