I seem to recall that the Transit Center has not opened....as has a similar problem....anyone know the update on Transit Center....?
The second phase (Underground) of the Center has not yet been fully funded or started.
The cracks in the steel beams in the Transit Center resulted from a skipped step in the installation welding procedure, NOT from the manufacture or quality of steel.
This skipped step (by the construction crew) on the jobsite was repeatedly undetected by SF Building Inspectors.
Hope this clears thing up.