415 miles completed.
The last two weekly reports had slower weekly rates - 7 and 6 miles (although Thanksgiving is in there).
Now that more than half of the 718 miles funded are finished (56%), we may have already crested our peak rate of construction (unless President Trump can pull a second term out of the hat, and add more money).
We could still be on track to complete the goal of 450 by year’s end.
I am not sure if you noticed, but a few weeks back, some more moved from pre-construction into under construction. Only 87 miles worth of segments have not yet broken ground.
Should a Biden Administration take office, there is a possibility that some segments underway, might continue to completion, depending on their status, the nature of their funding (direct appropriations, DOD Counter-narcotics, or diverted from Military Construction in the emergency declaration), and if all the land has been acquired for the right of way..
Thanx BeauBo. Crossing my fingers in hopes of completing in 2nd term