To: thinden

415 miles completed.

The last two weekly reports had slower weekly rates - 7 and 6 miles (although Thanksgiving is in there).

Now that more than half of the 718 miles funded are finished (56%), we may have already crested our peak rate of construction (unless President Trump can pull a second term out of the hat, and add more money).

We could still be on track to complete the goal of 450 by year’s end.

I am not sure if you noticed, but a few weeks back, some more moved from pre-construction into under construction. Only 87 miles worth of segments have not yet broken ground.

Should a Biden Administration take office, there is a possibility that some segments underway, might continue to completion, depending on their status, the nature of their funding (direct appropriations, DOD Counter-narcotics, or diverted from Military Construction in the emergency declaration), and if all the land has been acquired for the right of way..


5 posted on 12/05/2020 1:04:29 PM PST by BeauBo
[ Post Reply | Private Reply | To 4 | View Replies ]


To: BeauBo

Thanx BeauBo. Crossing my fingers in hopes of completing in 2nd term


6 posted on 12/05/2020 1:16:01 PM PST by thinden
[ Post Reply | Private Reply | To 5 | View Replies ]

Free Republic
Browse · Search
News/Activism
Topics · Post Article


FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson