Hi abb, Looks like it is a rotation movement. The 12" dia drain break behind the spillway wall undoubtably contributed to erosion of the wall anchoring. This wall has substantial mass. I have seen images of load transfer bars holes in sidewall to slab joints. These parallel load transfer bars could bind from a rotational component - rather than "slip" in the normal designed lateral expansion. However, I have not seen load transfer bar evidence on this wall side of the spillway. Only beveled mating joints (you can see this type of beveled joint in this image).
In any case, there seems to be a linking force between the mass of the sidewall and the spillway slab as the force to pull/rotate a slab would be substantial considering the slab anchor bars into rock (they drilled NX holes and then grout sealed the thick rebar anchor bars into the rock).
Thanks, ER333, and others. I’m visiting family so I’m not as attentive to the discussion as I could be.
I wonder if they intend on filling under that left corner or not.