Posted on 07/27/2011 4:04:40 AM PDT by TigerLikesRooster
Trouble continues at Fukushima nuclear plant's water treatment system
Jul 24 07:15 PM US/Eastern
TOKYO, July 25 (AP) - (Kyodo)A desalination device that forms part of the crisis-hit Fukushima Daiichi nuclear power plant's key water decontamination system halted for a number of hours Sunday in the latest glitch at the plant, Tokyo Electric Power Co. said late Sunday.
The plant operator said it resumed desalinating decontaminated water to be recycled as coolant for troubled reactors with a backup device about seven and a half hours after the halt occurred around noon, while continuing to cool the reactors with water supplemented from a nearby dam.
While looking into the cause of the latest trouble, Tokyo Electric said it will also add piping for the system's cesium decontamination component made by Areva SA of France because the volume of flow has not reached the expected level.
The water treatment system, which also comprises a cesium-absorbing device developed by Kurion Inc. of the United States, is designed to remove radioactive materials from and recycle the highly contaminated water accumulating at the plant as a side effect of initial emergency operations to cool overheating reactors.
(Excerpt) Read more at breitbart.com ...
P!
Saw over the weekend on FOX’s scroll they had a couple more quakes.
Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.