FALLUJAH — A 132-kilovolt substation, projected for completion in October, will result in more consistent and stable electricity for residents here.

The $14.8 million project is being managed by the Gulf Region Division, U.S. Army Corps of Engineers in Iraq, and funded by the Iraqi Relief and Reconstruction Fund.

The substation was damaged in a fire caused by circuit breaker failure in January 2005, and was identified by the Division’s Gulf Region District as a significant capacity-building project for the city.

Maj. Joseph Geary, the officer in charge of the District’s Fallujah resident office, praised the team for working steadfastly on the project and overcoming various issues, including getting the equipment on site in good condition.

For example, when a transformer arrived damaged, security concerns hindered its delivery to the repair facility in another province. GRD officials and the contractor worked together to negotiate the transport and repair of the critical component. Now, in coordination with Iraqi Security Forces, the project is progressing.

“It’s a great story where the contractor, GRD and the Deputy General from the Iraqi Ministry of Electricity all worked together to move this project closer to the finish line,” said Geary.

The transformer is at the factory for repair and is expected to be ready in approximately 60 days. In the meantime, the contractor is continuing to work on the switching equipment and other internal components.

When the 132-kilovolt substation is complete, the Fallujah Minister of Electricity will have more latitude in managing the power grid as it relates to allocating power from area to area.

Improvements at the Fallujah substation will also provide expansion capacity with the addition of another bay and main transformer.

During its peak construction season, construction of the Fallujah substation employed 40 Iraqi workers.

The Gulf Region Division, U.S. Army Corps of Engineers in Iraq has completed thousands of reconstruction projects in partnership with the U.S. government and the Government of Iraq. Since 2004, GRD has completed 4,626 projects throughout Iraq valued at more than $7.2 billion, and has 287 projects ongoing.


TOPICS: Culture/Society; Foreign Affairs; War on Terror
KEYWORDS: electricity; frwn; iraq; project

1 posted on 08/29/2009 9:51:16 AM PDT by SandRat
[ Post Reply | Private Reply | View Replies]

To: 91B; HiJinx; MJY1288; xzins; Calpernia; clintonh8r; TEXOKIE; windchime; freekitty; majhenrywest; ...
FR WAR NEWS!
If you would like to be added to / removed from FRWN,
please FReepmail Sandrat.

WARNING: FRWN can be an EXTREMELY HIGH-VOLUME PING LIST!!

2 posted on 08/29/2009 9:51:47 AM PDT by SandRat (Duty, Honor, Country! What else needs said?)
[ Post Reply | Private Reply | To 1 | View Replies]

To: SandRat

THanks FR

But isn’t it about time the Iraqis start paying for all this? After all they pull in 5 Billion a day in oil dough.


3 posted on 08/29/2009 10:27:16 AM PDT by ASOC (Cave quid dicis, quando, et cui)
[ Post Reply | Private Reply | To 1 | View Replies]

Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.

Free Republic
Browse · Search
News/Activism
Topics · Post Article

FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson