Milestone |
Completion Date |
Receive early site permit application |
10/21/03 - A
|
Press Release announcing receipt and availability |
11/07/03 - A
|
Federal Register notice (FRN) published for receipt and availability |
11/14/03 - A
|
FRN published announcing acceptance |
12/01/03 - A
|
FRN published for Notice of Intent (environmental scoping process) |
12/31/03 - A
|
Press Release announcing acceptance |
01/13/04 - A |
FRN published for mandatory hearing |
01/16/04 - A
|
Environmental scoping meeting |
01/21/04 - A
|
Scoping period ends |
02/12/04 - A
|
1st inspection complete |
02/13/04 - A
|
Deadline for filing petitions for intervention |
02/17/04 - A
|
Environmental site audit |
04/16/04 - A
|
Deadline for submitting contentions |
05/03/04 - A |
Environmental requests for additional information (RAIs) issued to applicant |
07/02/04 - A
|
Applicant submits response to environmental RAIs |
09/17/04 - A
|
Safety and emergency planning (EP) RAIs issued to the applicant |
09/21/04 - A
|
Applicant submits responses to safety and EP RAIs |
12/07/04 - A
|
Draft safety evaluation report (SER) issued |
04/07/05 - T
|
Draft environmental impact statement (EIS) to EPA, Issue Notice of Availability |
04/29/05 - T
|
ACRS subcommittee meeting on draft SER |
05/06/05 - T
|
ACRS full committee meeting on draft SER |
06/10/05 - T
|
Public meeting to discuss draft EIS |
06/14/05 - T |
Applicant submits responses to SER open items |
06/21/05 - T
|
2nd inspection complete |
06/23/05 - T
|
ACRS interim letter to Commission |
06/24/05 - T
|
End of draft EIS comment period |
07/14/05 - T
|
Optional final inspection complete |
09/08/05- T
|
Final SER issued |
10/21/05 - T
|
Regional Administrator's Letter |
11/22/05 - T
|
ACRS subcommittee meeting on final SER |
11/22/05 - T
|
ACRS full committee meeting on final SER |
12/08/05 - T
|
ACRS letter to Commission |
12/22/05 - T
|
Final EIS issued to EPA/Issue Notice of Availability |
12/23/05 - T
|
Final SER issued as NUREG |
01/28/06 - T
|
Atomic Safety and Licensing Board (ASLB) initial decision |
06/06/06 - T
|
Commission decision |
10/10/06 - T
|
So about three years to permit and it looks like they are behind schedule or have not updated the schedule.
I'll be glad when the nuke guys go back to their industry and leave petro/chem/fossel power to us "normal" industrial folks... ;^)