To: Tolerance Sucks Rocks

Well building it in 72 hours is a great thing but EPA permits will take 6 months.


7 posted on 07/20/2018 1:21:30 AM PDT by eartick (Stupidity is expecting the government that broke itself to go out and fix itself. Texan for TEXIT!)
[ Post Reply | Private Reply | To 1 | View Replies ]


To: eartick

“..but EPA permits will take 6 months.” Scratch that, 6 years.


8 posted on 07/20/2018 3:51:17 AM PDT by Beagle8U (Liberals can kiss my bitter clingers!)
[ Post Reply | Private Reply | To 7 | View Replies ]

To: eartick

I’m the project manager on a small bridge that crosses a non-fish bearing irrigation return drain. It’s taken over 3 years from initial funding through permitting to be approved for construction. Our issue now is the final permits were issued in June but our designated in-water fish window is between July and August and the bid processes takes 2 months, so we won’t be building this year.

Now were trying to negotiate a “floating” fish window that would allow us to bid and build based upon our bridge delivery schedule. It takes about 4 months after bid award to receive the manufactured girders, otherwise we have to wait until next July...


10 posted on 07/20/2018 4:12:44 AM PDT by shotgun ( .)
[ Post Reply | Private Reply | To 7 | View Replies ]