Spillway slope fill area noted via arrows. The Roller Compacted Concrete rise in elevation should accelerate in the coming days. The tapered outer RCC is deceptive in its additional bulk to the total volume required just to meet the angled slope noted by the arrows.
RCC is progressing quicker in the vertical lift placement. Good weather and no plant breakdowns would keep the schedule secure for the end of the month "meet-up" date to the new upper structural concrete section.
Still a lot of concrete left to be placed,
plus the erection of the temporary sidewalls.
I still say that filling in Moonbeam Canyon with those Bullet Trains of Jerry’s would have been faster than all this Roller Compacted Concrete substrate.
And I’m worried about getting my concrete driveway replaced by the end of October.