http://www.sacbee.com/news/state/california/water-and-drought/article159789184.html
Theyve demolished most of Oroville Dams troubled spillway. Whats next?
By Dale Kasler
dkasler@sacbee.com
July 05, 2017 2:47 PM
The preliminaries are just about over. Permanent structural repairs are about to begin at Oroville Dam.
Five months after an unprecedented emergency forced a mass evacuation, state officials said Wednesday theyre ready to start replacing the now-demolished lower portions of Orovilles main flood-control spillway.
Construction contractor Kiewit Corp. plans to install the first slabs of concrete Thursday in the lower 350 feet of the spillway chute. The so-called leveling concrete will create a smooth foundation for structural concrete that will be poured on top, said Jeff Petersen, Kiewits Oroville project director.
snip
Concrete placement in the spillway has begun using concrete pump.
http://www.parks.ca.gov/live/lakeorovillesra_spillway