Sabine Liquefaction Project Schedule
July 26, 2010 Submitted NEPA Pre-Filing Request
August 4, 2010 FERC Approval to use Pre-Filing Process
January 31, 2011 File NGA Section 3 Application
December 28, 2011 Issuance of Environmental Assessment / Environmental Impact Statement
January 31, 2012 File Initial Implementation Plan
April 16, 2012 Issuance of Authorization
3rd Q - 2012 Commence Construction
4Q 2015* Liquefaction Project In-Service
http://www.cheniere.com/terminals/sabine-pass/trains-1-4/project-schedule/
How were they able to sneak this past the greenies?
4Q 2015* Liquefaction Project In-Service
It's a private project. In Boston, it takes twice as long to rebuild one stinking bridge (Longfellow) under government contract.