Sabine Liquefaction Project Schedule

July 26, 2010 – Submitted NEPA Pre-Filing Request

August 4, 2010 – FERC Approval to use Pre-Filing Process

January 31, 2011 – File NGA Section 3 Application

December 28, 2011 – Issuance of Environmental Assessment / Environmental Impact Statement

January 31, 2012 – File Initial Implementation Plan

April 16, 2012 – Issuance of Authorization

3rd Q - 2012 – Commence Construction

4Q 2015* – Liquefaction Project In-Service

http://www.cheniere.com/terminals/sabine-pass/trains-1-4/project-schedule/


2 posted on 10/07/2015 5:36:10 AM PDT by thackney (life is fragile, handle with prayer)
[ Post Reply | Private Reply | To 1 | View Replies ]


To: thackney

How were they able to sneak this past the greenies?


4 posted on 10/07/2015 5:39:31 AM PDT by uglybiker (nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-nuh-BATMAN!)
[ Post Reply | Private Reply | To 2 | View Replies ]

To: thackney
3rd Q - 2012 – Commence Construction

4Q 2015* – Liquefaction Project In-Service

It's a private project. In Boston, it takes twice as long to rebuild one stinking bridge (Longfellow) under government contract.

8 posted on 10/07/2015 6:06:00 AM PDT by glorgau
[ Post Reply | Private Reply | To 2 | View Replies ]

Free Republic
Browse · Search
News/Activism
Topics · Post Article


FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson