113.7 miles so far.
Percent complete on these projects, does not equate with miles complete.
They have to submit a work breakdown structure to the Government Contracting Officer, and then tick off tasks to receive their periodic progress payments.
A lot of their tasks are preliminary work, like surveys, design, site prep, equipment and material staging.
For example, the 63 miles recently started in Arizona, is reported as 43% complete, but they only anticipate having two miles standing by October 1st.