June 2017 Update
- The terminal is 89% complete and on track for an in-service date in late 2017.
- There are currently more than 3,200 construction workers on site.
- All of the major equipment has been set in place and now the focus is on completing the installation of piping, cable trays, cables and cable terminations.
- Three of the five tower cranes used to transfer equipment onsite have been taken down and transported offsite.
- All barge loads have been received and all heavy haul deliveries have been transported.